Home NATIONAL NEWSACME Solar Commissions 70.19 MW BESS Across Two FDRE Projects in Rajasthan

ACME Solar Commissions 70.19 MW BESS Across Two FDRE Projects in Rajasthan

by Editor
0 comments
ACME Solar Commissions 70.19 MW BESS Across Two FDRE Projects in Rajasthan

ACME Solar Holdings Limited, through its wholly owned subsidiary ACME Greentech Seventh Private Limited, has commissioned the battery energy storage system (BESS) component of two firm and dispatchable renewable energy (FDRE) projects in Rajasthan. The commissioned BESS has a discharge capacity of 70.19 MW / 280.760 MWh, with an installed capacity of 70.19 MW / 320.960 MWh. The commissioning was completed on November 27, 2026.

The BESS has been commissioned across two sites. The commercial operation date (COD) for the same has been set for November 29, 2026.

At the first site, 17.23 MW / 68.92 MWh (installed capacity: 17.23 MW / 80.24 MWh) has been commissioned. This forms part of a 300 MW / 1,200 MWh FDRE project (installed capacity: 300 MW / 1,581 MWh) located at Village Kelan, Tehsil Chhatargarh, District Bikaner, Rajasthan. The project is connected at the Bikaner-III ISTS Pooling Station.

At the second site, 52.96 MW / 211.84 MWh (installed capacity: 52.96 MW / 240.720 MWh) has been commissioned. This is part of a 150 MW / 600.166 MWh FDRE project (installed capacity: 150 MW / 803.520 MWh) located at Village Sanawara, Tehsil Pokhran, District Jaisalmer, Rajasthan. The project is connected at the Fatehgarh-1 Substation.

At present, only the BESS component of the projects has been commissioned, while the corresponding renewable energy generation component is under development.

A Power Purchase Agreement (PPA) for the project has been signed with SJVN Limited.

You may also like

Leave a Comment