The Uttar Pradesh Electricity Regulatory Commission (UPERC) has approved Uttar Pradesh Power Corporation Limited’s (UPPCL) procurement of 600 MW of wind power from the Solar Energy Corporation of India Limited (SECI), with discovered tariffs ranging from ₹3.67 to ₹3.69 per kWh. The procurement covers seven wind power developers selected under SECI’s Tranche-XIX competitive bidding process and is expected to strengthen Uttar Pradesh’s renewable energy portfolio while supporting the state’s Renewable Purchase Obligation (RPO) requirements.
The Commission granted its approval on 16 November 2026 in Petition No. 2400 of 2026, concerning the long-term procurement of wind power connected to the Inter-State Transmission System (ISTS). UPPCL entered into a Power Sale Agreement (PSA) with SECI on 30 March 2026, followed by a supplementary agreement on 1 October 2026 to incorporate revised project details, including changes in the declared Capacity Utilisation Factors (CUFs).
Under the approved arrangement, K.P. Energy Limited secured 50 MW at the lowest tariff of ₹3.67 per kWh. Ganeko Three Energy Private Limited received 90 MW, while Waaree Forever Energies Four Private Limited was allocated 150 MW, both at ₹3.68 per kWh. Opera Lalpur Project Private Limited secured 25 MW at the same tariff. Greenpulse Power Private Limited received 125 MW, Vena Energy Aura Private Limited secured 62 MW, and Refex Vayu SPV 2 Private Limited was allocated 98 MW, all at ₹3.69 per kWh. Together, these allocations account for the entire 600 MW procurement capacity.
The declared CUFs across the selected projects range from 24.20% to 34.20%. Greenpulse Power has the highest declared CUF of 34.20%, followed by Opera Lalpur Project at 34%. The approved tariffs are exclusive of the applicable trading margin payable to SECI.
The procurement forms part of SECI’s 1,200 MW ISTS-connected wind power tender under Tranche-XIX. SECI conducted the tariff-based competitive bidding process and subsequently entered into Power Purchase Agreements (PPAs) with the selected developers for the supply of wind-generated electricity. The Central Electricity Regulatory Commission (CERC), through its order dated 14 October 2026 in Petition No. 179/AT/2026, adopted the tariffs discovered under the procurement scheme.
Following revisions in the declared CUFs of certain projects within the permissible limits of the bidding framework, UPPCL and SECI signed a supplementary PSA on 1 October 2026. The agreement incorporated the revised project-level details into the existing procurement arrangement. UPERC subsequently examined UPPCL’s proposal and approved the 600 MW procurement at the respective discovered tariffs in accordance with the tariff adoption by CERC.
The regulatory approval also addresses the commercial arrangements and payment security mechanisms governing the procurement. These provisions include escrow arrangements and irrevocable letters of credit to safeguard payment obligations under the long-term power supply agreement. The Commission also referred to the applicable provisions governing trading margins under the Central Electricity Regulatory Commission regulations. Where the prescribed escrow arrangement or irrevocable payment security mechanism is not provided in favour of the seller, the trading margin charged by the trading licensee is subject to a ceiling of ₹0.02 per kWh.
The approval comes as Uttar Pradesh looks to expand renewable energy procurement and strengthen the diversity of its electricity supply portfolio. The addition of 600 MW of wind power through an interstate procurement arrangement will provide the state with access to generation capacity developed by multiple independent power producers. Wind power can complement solar generation by diversifying renewable electricity sources and supporting a more balanced power procurement mix.
Procuring electricity through SECI also enables UPPCL to access competitively discovered tariffs without directly undertaking the development of the generation projects. The approval marks an important regulatory step in advancing the long-term procurement arrangement and completing the contractual framework for the selected capacity. The respective developers will undertake project implementation in accordance with their PPAs and applicable regulatory requirements.
With the 600 MW procurement receiving regulatory approval, UPPCL is advancing its efforts to secure additional renewable electricity through competitive bidding, supporting Uttar Pradesh’s clean energy transition and long-term power supply requirements.